Brough Relief Road (BRR) is an essential piece of infrastructure that links the new Brough South Development with the western side of Brough while also providing a new access for the Humber Enterprise Park (HEP) Enterprise Zone site.

 

This was the last piece of the infrastructure jigsaw that created 0.7 km of new public highway and unlocked 85ha of employment land (35ha of which has EZ status), creating 600 new jobs and accelerating the delivery of 550 housing units, 17,243m² of commercial space (A & B class uses), 4,088m² of community space (D1 & D2 uses) and improving public realm. It has reduced HGV and other traffic through Brough Town Centre.

‘Brough South’ led by the Horncastle Group and HEP led by Citivale are two employment related projects that have the potential to transform the growing town of Brough and make a significant contribution to the local and regional economy. To date the developments have been progressed in isolation but share a common infrastructure constraint which is access.

 

 

Project Dates

May 15, 2019 - October 31, 2025

Project Sponsor

East Riding of Yorkshire Council

Location

The scheme is located to the south east of the town of Brough in the East Riding of Yorkshire within the former Brough Aerodrome site on land controlled by Horncastle Group as part of the wider Brough South mixed use development and Citivale as part of the Humber Enterprise Park Enterprise Zone site. The project area is linear and extends for approximately 0.8 km in a roughly east-west direction from approximate National Grid Reference (NGR) SE941 262 at the western extent to NGR SE948 261 at the eastern extent. The closest postcode to the site is HU15 1ER.

Funding

TOTAL PROJECT EXPENDITURE £ 6,521,885.00
Profiled Achieved overall – up to end of Q4 23/24
LGF Spend £3,260,943.00 £3,260,943.00
Public Spend £1,630,471.00 £1,598,522.00
Private Spend £1,630,471.00 £1,477,264.00

Outputs

  Profiled Achieved overall – up to end of Q4 23/24
New Jobs 600 200
Construction Jobs 50 50
Housing units started 550 75
Housing units completed 550 75
Number of homes with improved broadband 550 75
New Roads (Km) 0.7 0.7
New cycleways completed and open for public use (Km) 0.7 0.7
Area of land reclaimed/redeveloped or reassembled (ha) 85 85
Commercial floor space created (m²) 17,243 3,000
Commercial floor space occupied (m²) 17,243 2,000

Approval Status

Business case approved

Delivery Status

Started

Last updated: August 14, 2024