The project delivers specific interventions to address major congestion ‘hot spots’ on the A1033 growth corridor in Hull. The interventions will provide improved traffic flow, especially at peak periods and improve facilities for public transport users, cyclists and pedestrians. The project includes the use of technology to provide improved communication with users of the network and to monitor traffic flow and air quality and forms an important strand within the project.
Project Dates
December 15, 2017 - September 16, 2022
Project Sponsor
Hull City Council
Location
Stoneferry Road, Hull
HU8 8ES
Funding
TOTAL PROJECT EXPENDITURE | £ 8,000,00.00 | |
Profiled | Achieved overall – up to end of Q4 23/4 | |
LGF Spend | £ 7,500,000.00 | £ 7,500,000.00 |
Public Spend | £500,000.00 | £500,000.00 |
Outputs
Profiled | Achieved overall – up to end of Q4 23/24 | |
Construction Jobs | 96 | 96 |
Resurfaced roads (Km) | 3.4 | 3.4 |
New roads (Km) | 1.6 | 1.6 |
New cycleways completed and open for public use (Km) | 1.6 | 1.6 |
Resurfaced shared use cycleway/footway (Km) | 3 | 3 |
Approval Status
Business case approved
Delivery Status
Completed